House Update #16

maltrab

Administrator
Staff member
Progress and a Hiccup this week, The gas hob is now fitted and working, the bathroom sink is installed,went to install the shower sides only to find they have sent the wrong size for the shower base so we have to wait on a replacement later this week, the bath and sides are installed and all the tiling finished.

All the vertical blinds arrived Friday,when unpacked we found they had not supplied the top fix brackets,so we have to wait for them, some Fancy German LED ceiling lights are fitted to two rooms, two left to do this week when the ceilings have there second coat of paint

We hope all the internal doors are back this week so they can be put back on, only 2 weeks to go
 